PROJECT UPDATE: - Friday, January 10, 2020
This stage of the project involves road works on the eastern side of the intersection for 20 metres from Milton Street along George Street. Traffic lights will also be installed.
After completion of this stage, full road closure will take place on George Street from Milton to Field streets while road works and traffic light installation are under way. This section of the road will be closed for approximately five weeks, weather permitting.
The construction of short-term parking in Evan Street, opposite Mackay State High School, and works to install a footpath to the western side of Milton Street are under way.