Nebia-Coningsby Road pavement rehabilitation

Share Nebia-Coningsby Road pavement rehabilitation on Facebook Share Nebia-Coningsby Road pavement rehabilitation on X (formerly Twitter) Share Nebia-Coningsby Road pavement rehabilitation on Linkedin Email Nebia-Coningsby Road pavement rehabilitation link

Road pavement rehabilitation works will commence on Nebia Coningsby Road, Balnagowan, in mid-November, weather permitting.

The works include 1.2 kilometres of new road pavement, roadside drainage, new property accesses to improve road safety on Nebia-Coningsby Road.

To minimise disruption to residents, the works will be completed in two stages.

Stage one includes approximately 530 metres of pavement near the intersection of Maraju-Yakapari Road. This section will be closed for the duration of the works with local access only.

Works will be undertaken between 6:30am and 6pm, Monday to Saturday.

Stage two works will commence from the completed section up to the Animal Care Centre on Nebia-Coningsby Road as soon as stage one is finished.

Impacted residents/businesses will be notified about the works and the traffic management arrangements prior to works starting.

Stage two is expected to be completed by late September 2027, weather permitting.

For further information, please contact our Community Engagement team at 1300 MACKAY (622 529) or email engagement@mackay.qld.gov.au.

This project is proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme (TIDS) and Mackay Regional Council.


Stay updated on this project by subscribing to its project update emails. Click the Stay Informed button on the right of this page. You will receive an email afterwards asking you to confirm your subscription.

Road pavement rehabilitation works will commence on Nebia Coningsby Road, Balnagowan, in mid-November, weather permitting.

The works include 1.2 kilometres of new road pavement, roadside drainage, new property accesses to improve road safety on Nebia-Coningsby Road.

To minimise disruption to residents, the works will be completed in two stages.

Stage one includes approximately 530 metres of pavement near the intersection of Maraju-Yakapari Road. This section will be closed for the duration of the works with local access only.

Works will be undertaken between 6:30am and 6pm, Monday to Saturday.

Stage two works will commence from the completed section up to the Animal Care Centre on Nebia-Coningsby Road as soon as stage one is finished.

Impacted residents/businesses will be notified about the works and the traffic management arrangements prior to works starting.

Stage two is expected to be completed by late September 2027, weather permitting.

For further information, please contact our Community Engagement team at 1300 MACKAY (622 529) or email engagement@mackay.qld.gov.au.

This project is proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme (TIDS) and Mackay Regional Council.


Stay updated on this project by subscribing to its project update emails. Click the Stay Informed button on the right of this page. You will receive an email afterwards asking you to confirm your subscription.