Project update: October 4, 2024
Share Project update: October 4, 2024 on Facebook Share Project update: October 4, 2024 on Twitter Share Project update: October 4, 2024 on Linkedin Email Project update: October 4, 2024 link
Image of Barren Creek Bridge during demolition.The demolition of Barren Creek Bridge has now been completed.
To accommodate the increased traffic on the detour route through Barren Creek and Barren Pocket roads, lights have been installed.
Fines and infringement notices have been issued to drivers not obeying the detour signage and lights. The route is regularly monitored by traffic management personnel and Queensland Police to ensure the safety of all road users.
The work is expected to be completed by late-December, 2024, weather permitting.
We appreciate your patience and consideration to other road users, while these essential works areContinue reading
Image of Barren Creek Bridge during demolition.The demolition of Barren Creek Bridge has now been completed.
To accommodate the increased traffic on the detour route through Barren Creek and Barren Pocket roads, lights have been installed.
Fines and infringement notices have been issued to drivers not obeying the detour signage and lights. The route is regularly monitored by traffic management personnel and Queensland Police to ensure the safety of all road users.
The work is expected to be completed by late-December, 2024, weather permitting.
We appreciate your patience and consideration to other road users, while these essential works are under way.
-
Project update: August 30, 2024
Share Project update: August 30, 2024 on Facebook Share Project update: August 30, 2024 on Twitter Share Project update: August 30, 2024 on Linkedin Email Project update: August 30, 2024 link
Emergency road closure notice
Calen-Mt Charlton Road at Barren Creek Bridge, Calen, is currently closed due to damage to the bridge.
Diversions have been set up via Barron Pocket Road and Barren Creek Road.
Temporary detour signs have been set up and council is working to implement more permanent traffic management and signage over the coming weeks.
Please allow extra time to reach your destination and follow all the signage and temporary traffic light signals that are in place.
The capital works that are scheduled to replace Barren Creek Bridge will begin as planned on Monday, September 9, 2024, weatherContinue reading
Emergency road closure notice
Calen-Mt Charlton Road at Barren Creek Bridge, Calen, is currently closed due to damage to the bridge.
Diversions have been set up via Barron Pocket Road and Barren Creek Road.
Temporary detour signs have been set up and council is working to implement more permanent traffic management and signage over the coming weeks.
Please allow extra time to reach your destination and follow all the signage and temporary traffic light signals that are in place.
The capital works that are scheduled to replace Barren Creek Bridge will begin as planned on Monday, September 9, 2024, weather permitting.
We apologise for any inconvenience caused by this closure and thank you for your cooperation.