Warland St open drain reconstruction - stage 1,2 & 3

Share on Facebook Share on Twitter Share on Linkedin Email this link

Works are underway on stage 1,2 & 3 of the Warland Street open drain reconstruction.

The drain is being reconstructed from Paradise Street to Warland Street and Warland Street to Milton Street in South Mackay to help reduce flooding in the area.

The works are being completed by contractor Bellwether and will be carried out Monday to Friday, 6.30am to 6.30pm and Saturday, 7am to 4pm.

These works are expected to be completed by June 2022, weather permitting.

As part of the project, the vegetation and trees in the drainage reserve will be removed to allow for the construction of the new drain and a number of fences will be replaced to be in line with property boundaries.

Property owners whose fences require replacement have been consulted, and the contractor will door-knock these properties prior to the commencement of these works.

During construction, residents will not be able to utilise the drainage reserve and traffic control will be in place on Paradise, Warland and Milton streets to allow work vehicles to enter/exit the work area. Please adhere to all signage and instructions.

There will be some minor noise and dust disturbances associated with these works, however appropriate controls will be in place to minimise these disturbances.

Should you have any questions or concerns about this project, please contact council’s project manager Chris Martin on 1300 MACKAY (622 529).

Works are underway on stage 1,2 & 3 of the Warland Street open drain reconstruction.

The drain is being reconstructed from Paradise Street to Warland Street and Warland Street to Milton Street in South Mackay to help reduce flooding in the area.

The works are being completed by contractor Bellwether and will be carried out Monday to Friday, 6.30am to 6.30pm and Saturday, 7am to 4pm.

These works are expected to be completed by June 2022, weather permitting.

As part of the project, the vegetation and trees in the drainage reserve will be removed to allow for the construction of the new drain and a number of fences will be replaced to be in line with property boundaries.

Property owners whose fences require replacement have been consulted, and the contractor will door-knock these properties prior to the commencement of these works.

During construction, residents will not be able to utilise the drainage reserve and traffic control will be in place on Paradise, Warland and Milton streets to allow work vehicles to enter/exit the work area. Please adhere to all signage and instructions.

There will be some minor noise and dust disturbances associated with these works, however appropriate controls will be in place to minimise these disturbances.

Should you have any questions or concerns about this project, please contact council’s project manager Chris Martin on 1300 MACKAY (622 529).

  • Update #1 - April 5, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The reconstruction of the Warland Street open drain between Paradise Street and Warland Street and Warland Street to Milton Street will continue until early-June, 2022.

    The project has been delayed by wet weather events.

    Stage 1 works - Completed. Vegetation and debris removed from the drain.

    Stage 2 works - Approximately 85 per cent completed. Remaining works include ramps, retaining wall, fencing and landscaping. To be completed early-May, 2022, weather permitting.

    Stage 3 works - Approximately 30 per cent completed. Remaining woks include concreting the open drain. To be completed by early-June, 2022, weather permitting.

    Work hours will remain the same - Monday to Friday, 6.30am to 6.30pm and Saturday, 7am to 4pm.

    Please note during construction residents will not be able to access the drainage reserve, and traffic control will be in place on Paradise, Warland and Milton streets. Please adhere to all signage and instructions.

    If your fence is being replaced as part of this project, the contractor will door-knock you prior to these works commencing.

    Should you have any questions or concerns about this project, please contact Bellwether Project Manager Emmett O'Manachain on 0437 696 753 or council's project manager Chris Martin on 1300 MACKAY (622 529).